On 14-15 July the EUMETCast receiving antenna was successfully installed on the roof of the UEM in Maputo.
MOZCast
Sunday, July 31, 2016
Thursday, July 14, 2016
Antenna installation has begun
Today (14/07/2016) the installation of the EUMETCast receiving Antenna has started and is expected to be finished tomorrow.
Sunday, July 10, 2016
Antenna Pole installed
The UEM completed the construction of the antenna pole on 1 July 2016 (picture below). The installation of the antenna was delayed as the EKU (Eumetsat Key Unit) must be replaced and delivery of the replacement took more than 3 weeks. The new EKU was delivered on 8 July.
The installation is now scheduled within for being performed during the 13 to 20 July.
The installation is now scheduled within for being performed during the 13 to 20 July.
Wednesday, May 11, 2016
Antenna and UPS Equipment is now on its way to Mozambique
The antenna dish, mount, pole and UPS equipment was now successfully picked up by the shipping company and will be transported to the UEM in Mozambique.
Monday, May 9, 2016
EKU, MoU and Antenna shipment delayed
The package containing the EKU and the Memorandum of Understanding (MoU) was blocked in customs in Botswana for more than a month now. The MESA team could today release the package from customs.
The MoU was signed on behalf of MESA and will be send to the UEM as soon as possible.
Also the shipment of the equipment suffered some delays as the shipping company had to change from express to global forwarding, because of the UPS batteries cannot be shipped by air. This problem never occurred before. The collection of the global forwarding was expected during last week but did not happened yet.
Due to this delays the current installation date for the antenna is begin of June.
The MoU was signed on behalf of MESA and will be send to the UEM as soon as possible.
Also the shipment of the equipment suffered some delays as the shipping company had to change from express to global forwarding, because of the UPS batteries cannot be shipped by air. This problem never occurred before. The collection of the global forwarding was expected during last week but did not happened yet.
Due to this delays the current installation date for the antenna is begin of June.
Friday, April 22, 2016
Procurement of Computer Equipment and Antenna
The computer equipment, uninterrupted power supply (UPS) and antenna equipment was procured by MESA-SAC THEMA and will be shipped today to the UEM.
Thursday, March 24, 2016